The concept of level 2 design introduced under the Road Project Preparatory Facility is an effective strategy, particularly when there is no guarantee that the designed roads will be constructed immediately after preparation. This strategy minimizes the risk of outdated designs while saving time and other resources.
Report Date
Project Name
Northern Road Connectivity Project
Project Number
42254-013
Report Source
Validation of self-evaluation
Country
Sri Lanka
Themes
Applicability
Project Cycle Stage
Implementation