Power System Expansion and Efficiency Improvement Investment Program (Tranche 3)

Sufficient lead time is needed for procurement, especially under the two-stage bidding process. Higher project readiness and clarity in employer’s requirements, including engineering designs and specifications, are critical inputs for bid documents.

Report Date
Project Name

Power System Expansion and Efficiency Improvement Investment Program (Tranche 3)

Project Number
42378-017
Report Source
Self-evaluation
Country
Bangladesh
Report Rating
Successful
Applicability
Project-level
Project Cycle Stage
Implementation
Topics
Procurement
Technical