Government budget regulations, particularly on official development assistance (ODA), the main source of ADB funding, need to be fully considered during appraisal as these could cause disbursement delays. In 2015, the allocation of ODA funds to project Implementation units was late and in 2016 no funds were allocated. This meant delays in project Implementation.