Guangxi Baise Vocational Education Development Project

Implementation arrangements are critical to the success of projects. Initial implementation progress under this project was mixed: while output 2 was progressing according to schedule, outputs 1 and 3 were not. At ADB's instance, the implementing agency (IA), the Baise University instituted reforms in the implementation arrangements, with the Vice President of the university replacing the project leading groups. Implementation shortfalls were subsequently promptly addressed even as the project management office, established by the executing agency (EA), the municipal government, was unable to provide support.