Determining and improving the effectiveness of large and complex projects are far more complicated than measuring progress against the indicators in the design and monitoring framewrok (DMF). The emphasis on quantitative measures, even if well considered, could result in displacing goals and/or inaccurately representing project success or failure. In the context of the COVID-19 pandemic and the Implementation timelines, some DMF targets were unrealistic. The project provided for formative evaluations but they were not closely coordinated with the DMF.