Resource constraints can impede the participation of smaller firms in ADB procurement as well as hinderCapacity development of counterpart agencies. Smaller firms struggled to respond appropriately in some bidding processes, which resulted in their being considered ineligible to participate. The project implementation unit experienced resource constraints, which hindered sustainedCapacity development throughout the project and the participation of outer islands officials in the training activities. Nevertheless, three implementing agencies demonstrated effective skills transfer from previous and ongoing related iniiatives, which contributed significantly to the project's success.