Second Central Asia Regional Economic Cooperation Corridor 2 Road Investment Program (Tranche 3 and Multitranche Financing Facility)

Performing an adequate level of due diligence and risk assessments at the early stage of project preparation increases the quality of project design and readiness. For example, preparatory work for procurement planning and administration of abnormally low bids (e.g., prequalification of bidders) supports and better streamlines the procurement process and avoids substantial changes in a project design and scope.