Early identification of the need to cancel subprojects and faster decision-making on project scope changes could shorten the extension of project implementation periods. This project's completion date was extended twice for a cumulative period of 3 years from the original completion of 31 December 2018. The first extension was until 31 December 2020 for the utilization of loan savings across different subprojects, necessitating a minor change in project scope that could have been shortened had the request for the scope change been made earlier. The second extension until 31 December 2021 was requested because of the significant delays encountered during the COVID-19 pandemic.