The identification of appropriate executing agency and implementing agency is essential for achieving the intended outcome and output targets. In this project, the Directorate General of Highways (DGH) should have been involved and appointed as the lead agency in identifying suitable sections for financing.
Report Date
Project Name
Trans Sumatra Toll Road Risk Monitoring
Project Number
54396-001
Report Source
Technical assistance completion reports
Country
Indonesia
Applicability
Project-level
Project Cycle Stage
Implementation
Keywords
OP6: Strengthening governance and institutional capacity
Topics
Stakeholder selection