Trans Sumatra Toll Road Risk Monitoring

Inappropriate stakeholder selection can create complications and challenges during implementation. The main issue during implementation is that the executing agency is not the owner of the toll road project, placing it in an unsuitable position to lead in identifying the sections for financing. Although revising the implementation arrangement by involving DGH as the implementing agency was a measure taken to address the issue, it turned out not to be sufficient.

Project Name

Trans Sumatra Toll Road Risk Monitoring

Project Number
54396-001
Report Date
Report Source
Technical assistance completion reports
Country
Report Rating
Applicability
Project Cycle Stage
Implementation
Keywords
OP6: Strengthening governance and institutional capacity