Project readiness filters and advanced actions are effective tools in mitigating the risk of startup and implementation delays. This project experienced a 2.5-year startup delay, which could have been minimized by implementing project readiness filters and advance actions, including procurement capacity building of the executing and implementing agencies during project preparation.
Report Date
Project Name
Pakse Urban Environmental Improvement Project
Project Number
43316-012
Report Source
Self-evaluation
Country
Lao People’s Democratic Republic
Sector
Themes
Applicability
Project Cycle Stage
Preparation