Khyber Pakhtunkhwa Water Resources Development Project

Frequent review missions are crucial to overcoming implementation challenges. The TA was administered by staff located in head office with good support from the Pakistan Resident Mission. However, ADB staff assignment changed during the TA implementation period; and the limitations and delays caused by the COVID-19 pandemic induced challenges to consultant management and client interaction. Frequent review missions significantly helped address these challenges.

Report Date
Project Name

Khyber Pakhtunkhwa Water Resources Development Project

Project Number
51249-003
Report Source
Technical assistance completion reports
Country
Pakistan
Report Rating
Applicability
Project Cycle Stage
Implementation