Khyber Pakhtunkhwa Water Resources Development Project

Additional financing and outsourcing complex tasks to specialized entities support successful TA implementation. ADB hired the World Wide Fund for Nature-Pakistan to conduct the ecological baseline survey. The TA secured financing of $300,000 on a grant basis from the Netherlands Trust Fund under the Water Financing Partnership Facility. The fund supported the conduct of feasibility studies for a main canal subproject. Without this fund, the feasibility studies would not have been completed.

Project Name

Khyber Pakhtunkhwa Water Resources Development Project

Project Number
51249-003
Report Date
Report Source
Technical assistance completion reports
Country
Report Rating
Applicability
Project Cycle Stage
Implementation