Supporting the Establishment of a CAREC Regional Infrastructure Projects Enabling Facility

Early consultation with relevant ADB units is essential to ensure a well-rounded TA design and a robust monitoring framework. These units' expertise can significantly enhance TA effectiveness and impact. By collaborating with experts from these units during the design phase, the possibility of overlooking critical components that are vital for a successful TA could be avoided.

Project Name

Supporting the Establishment of a CAREC Regional Infrastructure Projects Enabling Facility

Project Number
54344-001
Report Date
Report Source
Technical assistance completion reports
Report Rating
Applicability
Project Cycle Stage
Preparation
Keywords
OP7: Fostering regional cooperation and integration