Urban land acquisition in densely populated areas poses significant challenges. Compensation rates may rise during implementation, driven by urbanization rather than project schedules, potentially causing delays beyond the control of the project. Aligning civil engineering procurement with land acquisition progress is essential to prevent contractual disputes. Close collaboration, clear milestones, and effective communication mitigate risks. Establishing a resettlement information system aids in early issue identification, maintaining transparency.
Report Date
Project Name
Jiangxi Ji'an Sustainable Urban Transport Project
Project Number
45022-002
Report Source
Self-evaluation
Country
China, People's Republic of
Sector
Themes
Applicability
Project Cycle Stage
Implementation