Guangxi Southwestern Cities Development Project

Specific requirements for land acquisition and resettlement need to be completed prior to project implementation. Obtaining the necessary clearances and permits early on to meet the pertinent safeguards compliances can help in identifying any risk or grievance issues that can potentially delay the execution of project activities. Under the project, some components were substantially delayed due to the prolonged site turnover including the issuance of the appropriate permits, such as coastal land-use certificate, planning and construction permits, and utility lines.