Realistic estimation of project and contract duration is important. Inclement weather seriously hampered physical progress in project implementation, especially from August 2011 to February 2012. The contractor had difficulty coping with it, which significantly delayed the completion of works. A more realistic timeframe for implementing a road project should be formulated allowing for unpredictable local weather conditions and other contingencies so that resources can be deployed effectively and efficiently.