Delayed completion of preconstruction activities and advance action caused delays to all subsequent activities. ADB could have satisfied itself about project readiness in the key areas of detailed design, safeguards, procurement, and establishment of the project implementation unit.
Project Name
Road Sector Development Program
Project Number
32058-013
Report Date
Report Source
Independent project evaluation
Country