Preventive Health System Support Project

Need for market-based remuneration. The government's cost norm is too low and not competitive. Because of this, recruiting experienced senior national consultants (with the exception of retired government employees) remains a challenge. Training allowances are also too low. This also applies to its training allowances, which discourages participation by staff who must travel from where they live and work to take part. Future projects should include a clause that allows remuneration for consultants and allowances for staff training to be market-based.

Project Name

Preventive Health System Support Project

Project Number
34348-013
Report Date
Report Source
Self-evaluation
Country
Report Rating