The project road alignment should be fixed at project inception so that environmental, land acquisition andresettlement, and indigenous peoples’ safeguards could be prepared more comprehensively.
Project Name
CAREC Corridor 1 (Bishkek–Torugart Road) Project 3
Project Number
42399-023
Report Date
Report Source
Validation of self-evaluation
Country
Applicability