Independent technical studies are useful in addressing project-related grievances. The executing agency, in collaboration with ADB, determined that specific studies, including noise and vibration studies, had to be completed before proposing solutions to address the concerns of the complainants. While the proposed RAP was not accepted by the complainants, the technical studies proved useful in establishing the deficiencies of the IEE and could be built upon in addressing issues of similar nature.
Report Date
Project Name
Sustainable Urban Transport Investment Program - Tranche 3
Project Number
42414-043
Report Source
Self-evaluation
Country
Georgia
Sector
Applicability
Project-level
Project Cycle Stage
Implementation
Topics
Environmental
Social
Others