Procurement should be exhaustive. Developing a procurement strategy with proper analysis of market availability, operating environment, including capacity assessments of executing and implementing agencies, and risk management will help the project achieve its intended results in a timely manner. Where a project requires participation of government-owned universities or research centers, attention should be paid at project appraisal to para. 1.13 (c) of ADB’s Guidelines on the Use of Consultants (2013, as amended from time to time). If it does not apply, another procurement approach should be used to ensure the most capable entity is engaged.