Private Sector Development Project

Better cooperation between ADB and the executing agency in the preparation of the design and monitoring framework, as well as a more detailed assessment of appropriate project impact, outcome, and output performance indicators, could have improved performance monitoring, project evaluation, and possibly the project's ratings. In addition, a more detailed analysis of imprest account ceilings could have limited delays in project implementation. The imprest account ceiling for the line of credit facility had to be raised, with some difficulty, during implementation. This problem was fully addressed in the follow-up Inclusive Micro, Small, and Medium-Sized Enterprise Development Project (IMSMEDP).