CAREC Transport Corridor 1 (Bishkek–Torugart Road) Project 2

Greater project management capacity is necessary. MOTC and IPIG were effective in delivering the purely physical side of the project—the 75 km road civil works being completed within budget and the project’s closing date being extended to rehabilitate an additional 6 km village road using unutilized funds. However, the executing agency was not fully appreciative of the broader project design, including the nonphysical outputs and the importance of environmental safeguards, consultation, and monitoring.