The government needed to review and include interim milestone dates in the contract documents to ensure timely work completion and avoid extensions. The government also needed to institutionalize a safeguard system within the organizational framework of the project, particularly during implementation, for effective monitoring and supervision of and timely compliance with safeguard covenants.