Fuzhou Environmental Improvement Project

Alternative design options to avoid or minimize house demolition and resettlement should be explored thoroughly during detailed design and project implementation, particularly if the project is located in a rapidly urbanizing area. In the Fuzhou project, design options were largely limited by technical parameters such as flood discharge flows and gradients.

Project Name

Fuzhou Environmental Improvement Project

Project Number
35340-013
Report Date
Report Source
Self-evaluation
Report Rating