Emergency Assistance for Recovery and Reconstruction

Risks of combining emergency assistance projects with the more standard assistance packages. Providing fiscal resources was clearly urgent to ensure uninterrupted service and to reconstruct houses after the political disturbances. However, providing funds for undamaged but old water supply and sanitation systems was not as urgent and should have been completed as a separate project.