The importance of existing institutional capacity for carrying out changes in the technical aspects of the project design. The risks associated with a change in scope should be fully considered to prevent project failure.
Project Name
Financial Management Project
Project Number
30535-013
Report Date
Report Source
Validation of self-evaluation
Country
Themes