All components of projects should be treated as important and monitored from the early stages of project implementation. The difficulty of establishing technical support centers in five development regions of Nepal under the technical support components was mainly because the executing agency (EA) accorded them low priority and ADB did not follow up sufficiently.
Project Name
Small Towns Water Supply and Sanitation Sector Project
Project Number
31402-013
Report Date
Report Source
Self-evaluation
Country
Sector