Dali–Lijiang Railway Project

While work on the land acquisition and resettlement seemed to have progressed well, the executing agency—the West Yunnan Railway Company (WYRC)—should have been provided more assistance in its implementation given its inexperience with both PRC and ADB practices. As such, ADB assistance, through more frequent missions during the implementation period, could have provided the guidance needed for land acquisition and resettlement.