Skip to main content
Evaluation Lessons
  • Home
  • Countries
    • Afghanistan
    • Armenia
    • Azerbaijan
    • Bangladesh
    • Bhutan
    • Brunei Darussalam
    • Cambodia
    • China, People's Republic of
    • Cook Islands
    • Federated States of Micronesia
    • Fiji
    • Georgia
    • Hong Kong, China
    • India
    • Indonesia
    • Kazakhstan
    • Kiribati
    • Kyrgyz Republic
    • Lao People’s Democratic Republic
    • Malaysia
    • Maldives
    • Marshall Islands
    • Mongolia
    • Myanmar
    • Nauru
    • Nepal
    • Niue
    • Pakistan
    • Palau
    • Papua New Guinea
    • Philippines
    • Republic of Korea
    • Samoa
    • Singapore
    • Solomon Islands
    • Sri Lanka
    • Taipei,China
    • Tajikistan
    • Thailand
    • Timor-Leste
    • Tonga
    • Turkmenistan
    • Tuvalu
    • Uzbekistan
    • Vanuatu
    • Viet Nam
    • Australia
    • Japan
    • New Zealand
  • Sectors
    • Agriculture, natural resources, and rural development
    • Education
    • Energy
    • Finance
    • Health
    • Industry and trade
    • Information and communication technology
    • Multisector
    • Public sector management
    • Transport
    • Water and other urban infrastructure and services
  • Themes
    • Inclusive Economic Growth
    • Environmentally Sustainable Growth
    • Regional Integration
    • Private Sector Development
    • Governance and Capacity Development
    • Gender Equity and Mainstreaming
    • Knowledge Solutions
    • Partnerships
  • About
  • Home
  • Countries
  • Sectors
  • Themes
  • About

Highlands Region Road Improvement Investment Program - Project 2

The long procurement approval process needs to be factored into the design particularly of large infrastructure projects in PNG.

Project Name

Highlands Region Road Improvement Investment Program - Project 2

Project Number
40173-043
Report Date
31 Dec 2021
Report Source
Self-evaluation
Country
Papua New Guinea
Sector
Transport
Road transport (non-urban)
Applicability
Country-level
Project Cycle Stage
Implementation
Topics
Procurement - PNG

Related Lessons

Faster disbursement process. Disbursement was slower than specified in the conditions of contracts. In addition, local funds were disbursed much…


Combining the engineering, procurement, and construction (EPC) and operation and maintenance (O&M) into one package may yield more…


As in other sectors, the development of public-private partnerships (PPPs) in tourism requires a thorough market and business case analysis


All civil works project loans need to be delegated to ADB's country resident mission at the earliest date, to ensure closer monitoring, so…


Need for minimizing staff turnover in the executing agency during implementation. The PIU's (project implementation unit's) project…


Subscribe to our mailing list

6 ADB Avenue,
Mandaluyong City
1550, Metro Manila,
Philippines

 

Phone: +632 632 4444
Fax: +632 636 2444

Other ADB Websites

ADB Compliance Review Panel
Asia Pathways (ADBI Blog)
Asia Regional Integration Center
Asian Bonds Online
Asian Development Blog
Open Access Repository
Statistical Database System

IED Social Media

LinkedIn

Twitter

YouTube

©2024 Independent Evaluation - Asian Development Bank

Footer

  • About