Contractor Assessment. The project was affected by the unsatisfactory performance of two contractors and one supplier. Although such performance issues are usually observed in projects of similar nature, it is not simple to find a resolution through the bidding process or contract administration. Therefore, a well-planned performance monitoring system by the government linked to sanctioning of such entities may be a likely remedy.
Project Name
GMS - Cambodia Northwest Provincial Road Improvement Project
Project Number
42358-013
Report Date
Report Source
Self-evaluation
Country