Public Finance Management Reform Project

The DMF was not well designed and had deficiencies in the measurement of performance indicators for the project impact and outcome. Target dates should have been indicated the five outputs of the project involved the implementation of three components. These should have been integrated more closely with the outputs of the DMF.