Surkhandarya Water Supply and Sanitation Project

The project should not engage individual national consultants for construction supervision if there are many project sites due to limited capacity, unless mitigation measure are adopted. Significant inflation affected contracts. However, the contract amount was not adjusted due to the absence of price adjustment provisions in the contract documents, even in cases where the contract period was extended beyond 18 months. Price adjustments should be considered for contracts of less than 18 months when high inflation is likely to occur.

Project Name

Surkhandarya Water Supply and Sanitation Project

Project Number
40007-013
Report Date
Report Source
Self-evaluation
Country
Report Rating