The complexity of the program, as measured by the number and nature of outputs (and sub-outputs) and policy actions as an important factor in the degree of difficulty in implementation (footnote 7). There may have been too many conditions, i.e., policy actions, to be complied with for the releases of tranches 2 and 3 within the context of the anticipated timeframe for the program and in view of the limited capacity within the government.

Report Date
Project Name

Mizoram Public Resource Management Program

Project Number
41607-013
Report Source
Validation of self-evaluation
Country
India
Report Rating
Applicability