The complexity of the program, as measured by the number and nature of outputs (and sub-outputs) and policy actions as an important factor in the degree of difficulty in implementation (footnote 7). There may have been too many conditions, i.e., policy actions, to be complied with for the releases of tranches 2 and 3 within the context of the anticipated timeframe for the program and in view of the limited capacity within the government.
Project Name
Mizoram Public Resource Management Program
Project Number
41607-013
Report Date
Report Source
Validation of self-evaluation
Country
Themes
Applicability