ADB project documents need to be clear on how projects are to lead to sustainable results. The absence of consultants to address issues regarding the legal and technical aspects of O&M planning and funding, measures for cost recovery, tariff collection, and the metering system posed a risk to the sustainability of the water supply and sanitation subprojects. Future projects should include technical assistance that would implemented concurrently with the project. This technical assistance would review the tariff, assess its adequacy to generate sufficient revenue to sustain water supply systems, and evaluate the status of metering consumers. In line with this recommendation, ADB is currently supporting UWSCG’s ongoing review of its water tariff policy under a subsequent TA and loan.
Municipal Services Development Project and Municipal Services Development Project Phase 2