North Eastern Region Capital Cities Development Investment Program (Project 1)

Multiple executing agencies at national and state levels with overlapping mandates often result in complex mechanisms that can delay interagency communication, coordination, and timely decisions, thus resulting in implementation delays and ineffective contract management.