The stability of the ADB TA team and core staff of the TA executing agency from design stages to completion contributed to the achievement of the TA outputs and outcome, despite the change of director at the TA executing and implementing agencies in inception stages of TA implementation. ADB recruited, guided, and monitored the TA consultants, and ensured the quality of the TA outputs (milestone reports). Qualified international and national industry development experts were difficult to find, and the experts had been replaced a few times during TA implementation.
Project Name
Creating Enabling Environment fopr Gradual Rural-Urban Migration and Urban Settlements Development in Chuxiong Yi Autonomous Prefecture
Project Number
49279-001
Report Date
Report Source
Technical assistance completion reports
Country