Strategic Masterplan for Chittagong Port

The original TA implementation period was 32 months from May 2012 to December 2014. It was, however, estimated that consulting services would be required for the same duration. Considering the possible delay in government approval of TA effectiveness, as well as other unexpected delays during implementation, the implementation period should have been designed longer. In fact, political unrest in the country forced the consultant to demobilize key personnel from the site for a certain period.