North-West Frontier Province Urban Development Sector Project

There was a 3-year gap between the project preparatory technical assistance (PPTA) evaluations (in the last quarter of 1999) and the start (effectiveness) of the project (in the last quarter of 2002). Most structural and financial management plans, base maps, and priority subprojects therefore had to be reappraised at the start of the project, further delaying the project and straining limited capacity. To keep evaluations and project designs relevant, the time between project preparation and start up should not exceed 1 year.

Project Name

North-West Frontier Province Urban Development Sector Project

Project Number
27182-013
Report Date
Report Source
Self-evaluation
Country
Report Rating