The implementation arrangement underwent changes due to the dropping of the targeted component under an investment project, which could not be foreseen at the TA appraisal. This resulted in the change of the executing agency during implementation. The TA project activities was hampered as the output and outcome were tied up with another ongoing project that affected the delivery of output (ii)b. electrical connections to 500 HHs and billing by 200 women.
Project Name
Enabling Poor Women's Benefits from Enhanced Access to Energy in Hatiya Island
Project Number
48432-001
Report Date
Report Source
Technical assistance completion reports
Country