Skip to main content

Central Asia Regional Economic Cooperation Corridor 6 (Marakand–Karshi) Railway Electrification Project

Sustained efforts in providing adequate oversight and coordination between the government and concerned development partners are crucial for the timely implementation of a project. In particular, active and regular engagement among the stakeholders enhance monitoring and supervision of activities. This facilitates timely decision-making and helps minimize implementation issues. For example, procurement processes often require consistent coordination among the central government, development partners, and executing agencies, along with accurate cost estimates at appraisal, which are critical to the expected delivery of results.

Report Date
Project Name

Central Asia Regional Economic Cooperation Corridor 6 (Marakand–Karshi) Railway Electrification Project

Project Number
45067-005
Report Source
Validation of self-evaluation
Country
Uzbekistan
Report Rating