Sustained efforts in providing adequate oversight and coordination between the government and concerned development partners are crucial for the timely implementation of a project. In particular, active and regular engagement among the stakeholders enhance monitoring and supervision of activities. This facilitates timely decision-making and helps minimize implementation issues. For example, procurement processes often require consistent coordination among the central government, development partners, and executing agencies, along with accurate cost estimates at appraisal, which are critical to the expected delivery of results.
Project Name
Central Asia Regional Economic Cooperation Corridor 6 (Marakand–Karshi) Railway Electrification Project
Project Number
45067-005