Without a comprehensive and robust design and monitoring framework (DMF) and without undertaking the necessary updates, the level of project achievements against targets cannot be ascertained. In this project, the scale and character of planned physical works in one scheme were substantially altered during implementation, but the impact of this change on project effectiveness cannot be properly captured by the indicators in the DMF. Similarly, without conducting baseline and impact assessments, the economic viability of project investments cannot be reliably established.
Project Name
Greater Mekong Subregion Flood and Drought Risk Management and Mitigation Project
Project Number
40190-013
Report Date
Report Source
Self-evaluation
Country
Applicability
Project Cycle Stage
Preparation
Implementation
Completion