More time needs to be allotted for loan effectiveness if there are institutional changes to be made and implemented. The 90 days provided was insufficient when government bureaucracy requires review and approval up to the highest levels.
Report Date
Project Name
Padma Multipurpose Bridge Design Project
Project Number
35049-023
35049-033
35049-012
Report Source
Validation of self-evaluation
Country
Bangladesh