In MFFs, subsequent tranches should be processed and implemented to overlap with tranche 1 to maintain implementation momentum and achieve maximum benefits. The program’s tranches 2 and 3 were supposed to be approved in November 2017 and March 2018, respectively.
Project Name
Power Distribution Enhancement Investment Program - Tranche 1
Project Number
42401-015
Report Date
Report Source
Self-evaluation
Country
Themes
Applicability
Project Cycle Stage
Implementation