GAP performance was not successful overall, in part because of ambitious target setting, the absence of regular monitoring, reporting, and assessment of GAP achievement during the midterm review, inadequate GAP orientation during inception, and insufficient sensitivity and understanding of GAP implementation by stakeholders.
Report Date
Project Name
Water Resources Management Sector Development Program: Project Completion Report
Project Number
38558-013
Report Source
Self-evaluation
Country
Cambodia
Sector
Themes
Applicability
