Skip to main content
Evaluation Lessons
  • Home
  • Countries
    • Afghanistan
    • Armenia
    • Azerbaijan
    • Bangladesh
    • Bhutan
    • Brunei Darussalam
    • Cambodia
    • China, People's Republic of
    • Cook Islands
    • Federated States of Micronesia
    • Fiji
    • Georgia
    • Hong Kong, China
    • India
    • Indonesia
    • Kazakhstan
    • Kiribati
    • Kyrgyz Republic
    • Lao People’s Democratic Republic
    • Malaysia
    • Maldives
    • Marshall Islands
    • Mongolia
    • Myanmar
    • Nauru
    • Nepal
    • Niue
    • Pakistan
    • Palau
    • Papua New Guinea
    • Philippines
    • Republic of Korea
    • Samoa
    • Singapore
    • Solomon Islands
    • Sri Lanka
    • Taipei,China
    • Tajikistan
    • Thailand
    • Timor-Leste
    • Tonga
    • Turkmenistan
    • Tuvalu
    • Uzbekistan
    • Vanuatu
    • Viet Nam
    • Australia
    • Japan
    • New Zealand
  • Sectors
    • Agriculture, natural resources, and rural development
    • Education
    • Energy
    • Finance
    • Health
    • Industry and trade
    • Information and communication technology
    • Multisector
    • Public sector management
    • Transport
    • Water and other urban infrastructure and services
  • Themes
    • Inclusive Economic Growth
    • Environmentally Sustainable Growth
    • Regional Integration
    • Private Sector Development
    • Governance and Capacity Development
    • Gender Equity and Mainstreaming
    • Knowledge Solutions
    • Partnerships
  • About
  • Home
  • Countries
  • Sectors
  • Themes
  • About

Road Network Development Project

A few civil works contracts could not be completed even after extending the loan closing date by 18 months. The timeframe, working season, and site analysis should be considered prior to award of contract to ensure timely completion of the contracts.

Project Name

Road Network Development Project

Project Number
29472-013
Report Date
01 Aug 2011
Report Link
http://wcm.adb.org/projects/documents/road-network-development-project
Report Source
Self-evaluation
Country
Nepal
Sector
Transport
Road transport (non-urban)
Themes
Regional Integration
Gender Equity and Mainstreaming
Governance and Capacity Development
Private Sector Development
Report Rating
Successful

Related Lessons

Optimizing project scope and benefits requires careful analysis of the local context at design stage. Improved roads and market infrastructure…


Available evidence on using resource centers for extending professional support and services to the teachers shows it has not been very effective…


Improved rural connectivity is likely to be more effective in reducing poverty if supplemented by other initiatives such as investment in…


There may be merit in carefully reviewing donor coordination mechanisms to determine if there are more effective ways to coordinate structural and…


An effective project implementation entity is important when multiple financiers are involved, in order to ensure uniform standards in the…


Subscribe to our mailing list

6 ADB Avenue,
Mandaluyong City
1550, Metro Manila,
Philippines

 

Phone: +632 632 4444
Fax: +632 636 2444

Other ADB Websites

ADB Compliance Review Panel
Asia Pathways (ADBI Blog)
Asia Regional Integration Center
Asian Bonds Online
Asian Development Blog
Open Access Repository
Statistical Database System

IED Social Media

LinkedIn

Twitter

YouTube

©2024 Independent Evaluation - Asian Development Bank

Footer

  • About