Flood Emergency Reconstruction and Resilience Project

Well-defined targets for design and monitoring (DMF) indicators along with formulation of appropriate indicators’ baseline year and target values per year strengthen project design. A statement of percentage growth does not allow for a proper measurement of achievement. For example, the project DMF stated that at least 90% of selected flood protection and irrigation structures reconstructed and made more resilient by 2018”. However, it did not state the baseline and target values of the corresponding indicators and were not measurable.

Project Name

Flood Emergency Reconstruction and Resilience Project

Project Number
49038-001
Report Date
Report Source
Validation of self-evaluation
Country
Report Rating