Wuhan Urban Environmental Improvement Project

Ensuring the timely provision of counterpart funds reduces unnecessary implementation delays that could potentially lead to changes in project scope. Securing the financing and arrangements of counterpart funds at the outset avoids prolonged implementation of project activities. Specifically, adequate risk assessment of financing constraints and commitment of borrowers is essential for a more effective and smooth implementation.