Nuku'alofa Urban Development Sector Project

Timely capacity
development for executing agencies with limited experience in ADB’s procurement rules and in
safeguard requirements are important for an efficient project implementation. For example, retendering of TWB’s first works contract caused significant delays and could have been avoid

Project Name

Nuku'alofa Urban Development Sector Project

Project Number
42394-022
Report Date
Report Source
Validation of self-evaluation
Country
Report Rating